Tuesday 11 May 2010

Updating my Gantt chart


I have updated my Gannt chart to show the different stages of the project life cycle.
So far on this course I have learned why project fail and the different life cycles I could use in my project

1 comment:

  1. You have identified the relevant phases, added a baseline and milestone, identified realistic timescales, identified parallel and sequential processes and used project software correctly. You should identify the resources that need to be made available at each stage (e.g. you, access to software, etc.) Preparation complete’ isn’t really a task, maybe it should be a review task e.g. check preparation complete? You will obviously need to think about how you can check and what you would be looking for.

    In your next post, explain what you will be doing to review your project when you reach the milestones.

    ReplyDelete